Article 2. Projects of California Education Code >> Division 1. >> Title 1. >> Part 10. >> Chapter 12. >> Article 2.

The board may construct any project, and may acquire all property necessary therefor, on any terms and conditions as it may deem advisable. When any part of the work is to be done or performed by any public body or the United States jointly or in conjunction with the board, the portion of the cost of the project to be borne by the board may be turned over to the government of the United States or to any other public body, to be expended by it in the acquisition, construction or completion of the project.
The board may use for the payment of the costs of acquisition, construction or completion of any project any funds made available to the board by the State of California or any other funds provided by the board from any source, to be expended for accomplishing the purposes set forth in this chapter, together with the proceeds of bonds issued and sold pursuant to the State School Building Lease-Purchase Bond Law of 1976.
The board has full charge of the acquisition, construction, completion, and control of all projects authorized by them and may proceed with such work forthwith.
Title to all property acquired, constructed, or improved by the board and the revenues and income therefrom, is in the State of California. All such property, and the income therefrom are exempt from all taxation by the State of California or by any county, city and county, city, district, political subdivision or public corporation thereof.
(a) The board shall require the school district to make all necessary repairs, renewals, and replacements to ensure that a project is at all times kept in good repair, working order, and condition. All costs incurred for this purpose shall be borne by the school district.
  (b) In order to ensure compliance with subdivision (a) and encourage applicants to maintain all buildings under their control, the board shall require the applicant to do all of the following prior to the approval of a project:
  (1) Establish a restricted account within the general fund of the school district for the exclusive purpose of providing moneys for regular maintenance and routine repair of school buildings, according the highest priority to funding for the purpose set forth in subdivision (a).
  (2) Agree to deposit into the account established pursuant to paragraph (1), in each fiscal year for the term of the lease agreements of all projects constructed under this chapter, a minimum amount equal to or greater than 2 percent of the general fund budget of the applicant district for that fiscal year. This paragraph is applicable only to the following districts:
  (A) High school districts with average daily attendance greater than 300.
  (B) Elementary school districts with average daily attendance greater than 900.
  (C) Unified school districts with average daily attendance greater than 1,200.
  (c) For each project funded after July 1, 1998, the board shall require the applicant school district governing board to certify, as part of the annual budget process of the school district and beginning in the fiscal year in which the project is funded by the state, that a plan has been prepared for completing major maintenance, repair, and replacement requirements for the project. For purposes of this subdivision, the term "major maintenance, repair, and replacement" means roofing, siding, painting, floor and window coverings, fixtures, cabinets, heating and cooling systems, landscaping, fences, and other items designated by the governing board of the school district. The board shall require the school district's governing board to certify that the plan includes and is being implemented as follows:
  (1) Identification of the major maintenance, repair, and replacement needs for the project.
  (2) Specification of a schedule for completing the major maintenance, repair, and replacement needs.
  (3) Specification of a current cost estimate for the scheduled major maintenance, repair, and replacement needs.
  (4) Specification of the school district's schedule for funding a reserve to pay for the scheduled major maintenance, repair, and replacement needs.
  (5) Review of the plan annually, as a part of the annual budget process of the school district, and update, as needed, the major maintenance, repair, and replacement needs, the estimates of expected costs, and any adjustments in funding the reserve.
  (6) Availability for public inspection of the original plan, and all updated versions of the plan, at the office of the superintendent of the school district during the working hours of the school district.
  (7) Provision in the annual budget of the school district of a provision that states the total funding available in reserve for scheduled major maintenance, repair and replacement needs as specified in the updated plan, and an explanation if this amount is less than that specified in the updated plan. The reserve shall be maintained in the restricted account established pursuant to subdivision (b).
  (d) For purposes of this section, "good repair" has the same meaning as specified in subdivision (d) of Section 17002.
The board shall require the school district to insure against public liability or property damage in connection with any project.
(a) The board, by the adoption of rules, may establish priorities for the construction and leasing of projects to those school districts the pupils of which will benefit most. The board may make exceptions from established priorities when it determines that to do so will benefit the pupils affected.
  (b) The board may adopt rules establishing priorities for the acquisition and leasing of portable classrooms to county superintendents of schools that will most benefit pupils needing a county community school. The board shall require each county superintendent of schools who leases portable classrooms pursuant to Section 17017.2 to demonstrate that the portable classrooms are utilized solely for operation of a county community school.
Each school district that desires to lease a project for a grade level maintained by it, shall submit through its governing board an application therefor to the board in the form and number of copies that the board may prescribe. Immediately upon receipt of an application in the prescribed form accompanied by the required estimate of cost, a copy thereof shall be transmitted by the board to the Director of General Services. Each copy of the application shall be accompanied by a statement of the estimated cost of the project certified by an architect or structural engineer, and by layout plans showing the entire construction project. Before the board approves an application for a construction project, it shall establish cost standards for all new construction included therein. The cost standards shall not exceed typical comparable new construction by school districts in the same area, or if there has been no new construction by school districts in the area, the cost standards shall not exceed the reasonable current cost of similar construction in the area. The board shall determine such typical current costs or such reasonable current costs. In applying cost standards the board shall take into account the size and type of the construction proposed and may make any deviations that in its judgment are justified. When a standard has been set by the board to cover any individual apportionment, no project shall be approved by the board in excess of the standard, unless the board shall find that in view of a subsequent increase in building costs an adjustment is warranted. No contract shall be let for a construction project which has been approved by the board if the cost exceeds the construction cost standards fixed by the board under this section for the new construction.
(a) The West Contra Costa Unified School District shall be ineligible for any state school facilities funding for a period of five years from June 30, 1993, or until the date of the final payment on its entire debt to the state, including both principal and interest, whichever is later. Notwithstanding the above, the school district may continue to receive funding for deferred maintenance activities and for those purposes specified in subdivision (b).
  (b) The State Allocation Board shall approve funding for only those Richmond Unified School District State School Building Lease-Purchase Program projects which were approved for Phase II apportionments on or before April 1, 1993. All West Contra Costa Unified School District projects may be considered for funding by the State Allocation Board either in five years or after the complete repayment of the loan established under Section 41471, whichever is later.
  (c) In the event that the State Allocation Board approves the replacement of the existing Belding Elementary School with funds currently allocated for the modernization of the Harry Ells Middle School and the Samuel Gompers Middle School, that approval shall be considered allowable exemption under subdivision (b). Authority for this exemption is repealed on November 1, 1993, if approval of Phase III construction apportionment for the replacement of the existing Belding Elementary School has not occurred. In allowing for the possibility of this exemption, it is not the intent of the Legislature to interfere in any way with the decisionmaking authority and process of the State Allocation Board. It is the intent of the Legislature that a proposal to replace the existing Belding Elementary School with funds currently allocated to the modernization of the Harry Ells Middle School and the Samuel Gompers Middle School be submitted to the State Allocation Board under its existing procedures and policies. The State Allocation Board's decision shall be based on the merits of the proposal, not this exemption authority. Specifically, this subdivision may not be used as justification for approval of a project to replace the Belding Elementary School.
  (d) Any properties or facilities designated by the school district to be used for other than school purposes to generate capital to repay the outstanding debt shall be ineligible for deferred maintenance funding. Should any facilities receive funding for those purposes after the enactment of this legislation, and later be declared available for purposes intended to repay the debt, the value of state funding received for deferred maintenance at that facility shall be deducted from ongoing or future deferred maintenance projects in the district. If no projects are available for offset of apportionments, the value of the deferred maintenance performed will be added to the outstanding loan balance.
(a) The board may own, have maintained, and lease portable classrooms to any county superintendent of schools who provides a county community school program, as defined in Section 1986. These portable classrooms shall be adequately equipped to meet the educational needs of these pupils, including, but not limited to, sinks and restroom facilities.
  (b) The board, with the advice of the Superintendent of Public Instruction, may have portable classrooms constructed, furnished, or equipped, and may otherwise require whatever work is necessary to place portable classrooms for county community schools where needed, including the acquisition and preparation of sites. The board shall, in consultation with the Superintendent of Public Instruction, establish standards for the acquisition of land, with land acquisition limited to no more than 10,000 square feet per portable classroom, waivable by the board only as needed to meet local zoning and land use requirements or health and safety considerations.
  (c) A county superintendent of schools who desires to lease portable classrooms shall have prepared for the board's use performance specifications for portable classrooms and bids for their construction that can be solicited from more than one responsible bidder.
  (d) No portable classroom shall be made available to a county superintendent of schools unless the county superintendent of schools furnishes evidence, satisfactory to the board, that the county superintendent of schools has no other facility available for rental, lease, or purchase in the geographic service area that is economically or otherwise feasible.
  (e) If at any time the board determines that a lessee's need for particular portable classrooms that were made available to the lessee pursuant to this chapter has ceased, the board may take possession of the portable classrooms and may lease them to other county superintendents of schools or, if there is no longer a need for portable classrooms, the board may dispose of them to public or private parties in the manner it deems to be in the best interest of the state.
  (f) This section does not limit the authority of a county superintendent of schools to provide facilities without assistance from the board for pupils who are enrolled in a county community school.
(a) The board may approve, in whole or in part, an application submitted by a school district under Section 17017 or 17020 in an amount not exceeding the amount applied for as the board may deem appropriate.
  (b) The board may, upon approval of the application, in whole or in part, and subsequently from time to time, make apportionments of project funding not exceeding in the aggregate the total amount determined by the board under subdivision (a) for the portion or portions of the project for which the board determines the district is ready to proceed. Subsequent to the board's approval of a project, any requirement imposed by the board that the compliance of the project with building cost or area standards and related guidelines adopted by the board be established as a condition of the apportionment of funds under this chapter shall be satisfied, as to a project for a self-certifying district, by the certification by the district of that compliance. In addition, the board shall not require that estimates of average daily attendance be updated as to that project more often than once every 12 months subsequent to the board' s approval of the project. The self-certifying district shall maintain documentation of the compliance certified pursuant to this subdivision as may be required by the board, and that compliance shall be subject to subsequent audit as the board may direct.
  (c) Whenever a district files an application, the board shall require the district to submit to the board and the State Department of Education a five-year plan for construction and rehabilitation of school facilities, and to obtain the written approval of the department that the plan complies with standards that are established by the department for this purpose to ensure that the applicant district has adequately anticipated its school facilities needs and identified funding sources as necessary to meet those needs. The plan may be adjusted to reflect adjusted growth targets.
  (d) The board shall not approve any application under this chapter after January 1, 1990, unless accompanied by a study examining the feasibility of implementing in the district a year-round multitrack educational program that is designed to increase pupil capacity in the district or in overcrowded high school attendance areas by at least 20 percent.
  (e) The board may waive subdivision (d) or the requirements of Section 17017.7, or both, if a school district demonstrates that these requirements will result in a particular educational or financial hardship to the district. Further, the board shall waive subdivision (d), if it finds that there is clear hardship to a district due to declining enrollment or no growth.
Notwithstanding Section 17017.7, the definition of "substantial enrollment" set forth in that section shall apply only to elementary and unified school districts. For a high school district, "substantial enrollment in multitrack year-round schools," for the purposes of Section 17017.7, means that at least 30 percent of the pupils enrolled in the high school district are enrolled in multitrack year-round schools, or that 40 percent of the pupils enrolled in public school in kindergarten and grades 1 to 12, inclusive, within the boundaries of the high school attendance area for which the school district is applying for new facilities are enrolled in multitrack year-round schools. In addition, a high school district shall be deemed to have a substantial enrollment in multitrack year-round schools for purposes of Section 17017.7 if, at the option of the district, the entire high school to be constructed is to operate on a multitrack year-round basis.
(a) Notwithstanding any other provision of this chapter, priority for the approval of project funding for new construction under this chapter, shall be as follows:
  (1) First priority for construction funds shall be given to school districts with a substantial enrollment in multitrack year-round schools requesting state funding for 50 percent of the cost of a project that would be constructed to operate on a multitrack year-round basis.
  (2) Second priority shall be for school districts with a substantial enrollment in multitrack year-round schools requesting state funding for the entire cost of a project that would be constructed to operate on a multitrack year-round basis.
  (3) Third priority shall be for school districts without a substantial enrollment in multitrack year-round schools requesting state funding for 50 percent of the cost of a project to operate on a multitrack year-round basis.
  (4) Fourth priority shall be for school districts without a substantial enrollment in multitrack year-round schools requesting state funding for the entire cost of a project that would be constructed to operate on a multitrack year-round basis.
  (5) Fifth priority shall be for school districts with a substantial enrollment in multitrack year-round schools requesting state funding for 50 percent of the cost of a project that would not operate on a multitrack year-round basis.
  (6) Sixth priority shall be for school districts with a substantial enrollment in multitrack year-round schools requesting state funding for the entire cost of a project that would not operate on a multitrack year-round basis.
  (b) The board shall not restrict the availability of funding for construction of multitrack year-round schools, from any funding source available to the State School Building Lease-Purchase Fund, but shall make approval of project funding for those projects the first priority in accordance with this section.
  (c) "Substantial enrollment," for the purposes of this section, means enrollment of at least 30 percent of district pupils in kindergarten and grades 1 to 6, inclusive, or 40 percent of pupils in kindergarten and grades 1 to 12, inclusive, in the high school attendance area for which the school district is applying for new facilities. The calculation set forth in this subdivision, as to a self-certifying district, shall be made by the district, in accordance with any standards governing that calculation that are adopted by the board. The calculation shall be certified by the district to the board and used by the board for the purposes of this section. The self-certifying district shall maintain documentation of the calculation as may be required by the board, and the calculation shall be subject to subsequent audit as the board may direct. If a self-certifying district is found by the board to have materially misrepresented its pupil enrollment pursuant to this subdivision, the board may impose either or both of the penalties set forth in paragraphs (1) and (2) of subdivision (b) of Section 17041.2, in accordance with that section.
  (d) "Multitrack year-round school," for purposes of this section, means a school for which the applicant district demonstrates that both of the following criteria are satisfied:
  (1) The pupils are divided into three or more groups or tracks, which rotate attendance so that, for a majority of schooldays during the school year, at least one group or track is not attending the school while all other groups or tracks are in attendance.
  (2) The operation of the school on a multitrack year-round basis has resulted in an increase in enrollment capacity.
  (e) Notwithstanding any other provision of this section, the State Allocation Board may continue to implement any year-round school priority provisions for hardships adopted prior to September 1, 1990.
(a) Notwithstanding any other provision of law, a project shall be accorded, subject to subdivision (b), the priority status that otherwise is accorded under Section 17017.7 to a project for which state funding is requested for only 50 percent of the cost, if all of the following conditions are met:
  (1) The applicant district documents to the satisfaction of the board that it has incurred bonded indebtedness in an amount not less than 95 percent of the bonding capacity of the district. "Bonded indebtedness" for the purposes of this section includes, but is not limited to, funding provided pursuant to Chapter 2.5 (commencing with Section 53311) of Part 1 of Division 2 of Title 5 of the Government Code.
  (2) The applicant district agrees that up to 95 percent of the unexpended bonding capacity of the district, existing on or after the date of the district's first application for project funding pursuant to this section, shall apply toward the cost of projects.
  (3) Either of the following apply:
  (A) The applicant district agrees that developer fees imposed pursuant to Section 17620 shall apply toward the cost of projects for which the district requests state funding pursuant to this chapter, not to exceed 50 percent of the cost of any project. Fees needed for interim housing for capital outlay purposes for modernization and new construction projects, school district administration capital outlay projects, and capital outlay projects for transportation needs, are exempt from this requirement.
  (B) The applicant is a school district with an average daily attendance of 2,500 or less.
  (b) An applicant district qualifying for the priority status described in subdivision (a) as to any project shall continue to be accorded that status for all subsequent projects under this chapter until the time that the bonding capacity of the district determined for purposes of that subdivision increases by 20 percent.
  (c) The condition set forth in paragraph (2) of subdivision (a) shall apply until either the applicant district's eligibility under this section terminates pursuant to subdivision (b), or funding for the district is approved and apportioned under this chapter for a project for which 50 percent or more of the cost is provided by the district from funding sources other than any state program administered by the board, whichever occurs first.
  (d) Notwithstanding any other provision of law, as to any project for which priority status is accorded pursuant to subdivision (a), the estimate of average daily attendance for the applicant district may be calculated, upon request of the district, in the manner set forth in subdivision (a) of Section 17040.3.
  (e) The board may recalculate program allowances and apportionments pursuant to this section.
In approving applications pursuant to this chapter, the board shall encourage the design and construction of facilities which will conserve unreplenishable energy resources by consideration of alternate design and insulation concepts as well as unconventional energy sources. In so doing, the board may increase cost allowances to reflect the difference between conventional and unconventional concepts when the board is satisfied that the life cycle cost of the project is not expected to exceed the life cycle cost of a conventionally designed project.
(a) The Legislature intends for the board to encourage school districts to utilize alternative methods to fund school facilities.
  (b) The board shall approve applications pursuant to the requirements of this section that request the board to share a portion of the cost of projects constructed pursuant to the Mello-Roos Community Facilities Act of 1982, as set forth by Chapter 2.5 (commencing with Section 53311) of Part 1 of Division 2 of Title 5 of the Government Code. The board shall disregard the fact that structures have been constructed in accordance with that act, and neither consider nor approve any application for cost sharing until the time that the applicant school district would have become eligible for approval of its application during the normal process established for considering and approving applications.
  (c) The board shall approve applications for cost sharing based on both of the following factors:
  (1) Estimates of average daily attendance at the time the application is considered.
  (2) The amount of cost sharing requested.
  (d) The costs shared by the board shall be an amount equal to the cost that would have been allowed for the project had it been originally approved pursuant to this chapter less 5 percent per year depreciation, exclusive of land, for each year that the project was constructed in advance of the application approval, but no more than the lesser of an amount equal to 75 percent of the allowable cost of the project or the principal amount of any outstanding callable bonds and other debts incurred to finance the project under the Mello-Roos Community Facilities Act of 1982.
  (e) If the board utilizes a point system to prioritize applications for funding, the computation of priorities for an application pursuant to this section shall be increased by 4 percent for each year from the date of construction of the project to the date of approval of the cost-sharing application.
(a) Notwithstanding any other provision of law to the contrary, a school district that has, within the previous 24-month period, constructed or otherwise acquired school facilities with 100 percent local funding, may apply for funding for the construction of a gymnasium or multipurpose room on the site where it constructed or otherwise acquired school facilities with 100 percent local funding.
  (b) If the State Allocation Board determines that the schoolsite does not have adequate gymnasium or multipurpose room facilities, the board may approve the application pursuant to this section.
  (c) For an application approved pursuant to this section, the board shall grant the school district a credit against its local matching share requirement of up to 50 percent of the costs of the project or the total local funds expended by the school district on any school facilities funded by 100 percent local funds within the immediately preceding 24-month period, whichever is less.
  (d) For an application approved under this section, the project shall be accorded the priority status that is otherwise accorded under Section 17017.7 to a project for which state funding is requested for only 50 percent of the costs.
  (e) As used in this section "100 percent local funding" includes construction or acquisition of a school facility with 40 percent funding from the general fund of the school district and with the remainder of the local funding from the sale of surplus school property.
Before the board approves any project that includes the acquisition of furniture or equipment, it shall establish current cost and quality standards for furniture and equipment, including, but not limited to, educational technology hardware. The standards shall not exceed the cost and quality of furniture and equipment for comparable facilities purchased by school districts in the same area. The standards shall consist of furniture and equipment costs for each type of classroom or pupil station having different cost criteria. The standards shall be reviewed quarterly by the board and adjustments made in accordance with actual current costs. When cost and quality standards have been adopted by the board, the standards shall not be exceeded unless a subsequent increase in actual current costs warrants an adjustment. Before the board approves a project for the replacement, reconstruction, or alteration of, or addition to, a school building, full consideration shall be given to all usable furniture and equipment existing in the applicant district. The board may approve all or a portion of the amount applied for.
(a) Any applicant school district may contract with a firm, as defined in Section 4525 of the Government Code, for construction project management services to assist in the development or implementation of a project for which the district has applied for funding under this chapter, subject to the requirement that a performance bond be required from all building contractors hired to construct the project in order to ensure the completion of performance under the contract.
  (b) That portion of any contract, as described in subdivision (a), concerning the final phase of construction of the project, shall be submitted by the applicant district to the board for approval. If the board does not approve, reject, or recommend modifications to, that contract portion within 15 business days after receiving that contract information, that portion of the contract shall be deemed to be approved by the board.
  (c) From the amount of funding approved by the board under this chapter for any project, the board shall authorize the expenditure of funds for the costs of construction project management services provided to the project, as described in subdivision (a), where the board finds that the contracting for those services was necessary and appropriate to the school district's development or implementation of that project.
For a school district having an average daily attendance of 2,500 or less for the prior fiscal year, the board may approve, subject to the building cost standards established under this chapter, a supplemental apportionment up to five thousand five hundred dollars ($5,500) for any new construction project, and up to one thousand three hundred twenty dollars ($1,320) for any other project approved under this chapter, as reimbursement for administrative expenses incurred by the district in filing the application for the project. The amount of the supplemental apportionments shall be adjusted in 1990, and every two years thereafter, by the board at its January meeting, which adjustment shall be in an amount equal to the amount of the adjustment for inflation set forth in the statewide cost index for class D construction.
(a) Notwithstanding other provisions of this chapter, in order to expedite a total school facility a school district may first apply for a project which includes only the advance purchase of the land and preparation of plans and specifications. The acquisition of the site and the plans preparation shall be based on the justification documents for the total school facility. The school district may apply for a subsequent project or projects to complete the total school facility.
  (b) Any application filed pursuant to this section shall be subject to all provisions of this chapter generally applicable to project applications, to the extent not in conflict with this section.
  (c) Any estimate of average daily attendance made by an applicant district for the purpose of justifying an application pursuant to this section may be made for up to and including two years longer than the period of time permitted by Section 17040.
  (d) Beginning in the fifth fiscal year following the fiscal year in which any apportionment is made to a school district pursuant to this section, the district shall repay the apportionment, with interest, in 10 equal annual installments, unless and until the district has qualified for an apportionment pursuant to an application for utilization of the site under this chapter. These repayments shall constitute rent, and shall be in addition to any other rents or fees for which the district is obligated under Section 17032. The board may waive any obligation of repayment under this subdivision to the extent that the board finds that the obligation will result in an extreme hardship upon the district.
  (e) The school district may apply for a subsequent project or projects to complete the total school facility.
No project shall be approved for the reconstruction, modernization, or replacement of any school building that was constructed or reconstructed less than 30 years, or, in the case of any portable classroom, as defined in subdivision (e) of Section 17042.5, less than 20 years, prior to the date of approval of the project applied for under this chapter.
(a) For purposes of this chapter, "modernization" or "renovation" means any modification of an existing structure, the costs of which do not exceed 25 percent of the replacement cost of that structure.
  (b) No project shall be approved for the modernization of any school facility unless and until both of the following are demonstrated to the satisfaction of the board:
  (1) The project will enhance the capacity of the facility to achieve one or more educational purposes.
  (2) The resulting pupil capacity of the facility, as measured in units of average daily attendance, will equal or exceed 80 percent of the facility's maximum capacity as determined under the board standards established under this chapter.
  (c) No project shall be approved for the modernization of any school facility that was constructed less than 30 years prior to the date of the approval of the project applied for under this chapter.
  (d) The State Allocation Board may waive the requirement in subdivision (c) if the building has been declared by the Office of the State Architect to be, or is in imminent danger of becoming, a health or safety hazard to the pupils. This determination may only be made in the case of a natural disaster, for example, fire, flood, or earthquakes, or as a result of a determination by a qualified engineer, and agreed to in writing by the Office of the State Architect.
Notwithstanding the limitation set forth in subdivision (a) of Section 17021.3, the costs of a modernization or renovation project funded under this chapter may exceed 25 percent of the replacement cost of an existing structure where the costs in excess of that amount are funded by the district exclusively from sources other than any state program administered by the board. For each project, the total costs of the modernization or renovation project, as supplemented pursuant to this section, may not exceed 50 percent of the replacement cost of the existing structure except to the extent of those costs funded by the district, from sources other than any state program administered by the board, that are expended to conform that structure to current building standards, in which event the total costs of the project may not exceed 75 percent of the replacement cost of the structure.
Except as provided in Section 17041, the board shall not approve any new school facilities for any applicant school district or county superintendent of schools until it first has made a determination that the applicant will utilize all existing facilities and sites to the extent economically and practically feasible. The board may also require the applicant to explore cooperative efforts with adjacent districts or, in the case of county superintendents of schools, with adjacent county superintendents of schools, in order that all existing or planned facilities in the general area of need shall be utilized.
(a) The funding for any reconstruction project approved by the board pursuant to this chapter that meets the requirements set forth in subdivision (b) shall include all of the following, not to exceed the total cost of the reconstruction project or 75 percent of the replacement cost of the facility to be reconstructed, whichever is less:
  (1) Twenty-five percent of the replacement cost of the facility.
  (2) A funding entitlement to the extent that the reconstruction will result in an increased capacity of the facility to house pupils, calculated pursuant to the cost standards for new construction established by the board under Section 17017.
  (3) Any costs incurred by the district as required to ensure that the facility, as reconstructed, complies with applicable structural safety standards for school buildings pursuant to Article 3 (commencing with Section 17280) and Article 6 (commencing with Section 17365) of Chapter 2 of Part 10.5, and Article 7 (commencing with Section 81130) and Article 8 (commencing with Section 81160) of Chapter 1 of Part 49.
  (b) In order to qualify for the funding entitlement set forth in subdivision (a), a school district reconstruction project shall be required to meet all of the following conditions:
  (1) The facility to be reconstructed is at least 30 years old as of the date the application is filed.
  (2) The cost of the reconstruction project exceeds 25 percent of the replacement cost of the facility.
  (3) The reconstruction will result in an increased capacity of the facility to house pupils.
  (c) No reconstruction project shall be approved under this chapter for which the total cost exceeds 75 percent of the replacement cost of the facility to be reconstructed.
Nothing contained in this chapter shall be construed as changing the powers and duties of the Department of Education or the Department of General Services in respect to schoolsites and the construction of school buildings as contained in Chapter 1 (commencing with Section 17211) and Chapter 2 (commencing with Section 17251) of Part 10.5.
(a) The board shall not authorize the selection of any schoolsite, or a contract for the construction of any new school building, or for any addition to, or alteration of, any existing building, for lease-purchase to any school district, unless the applicant district has obtained the written approval of the State Department of Education that the site selection, and the building plans and specifications, comply with the standards adopted by the department pursuant to subdivisions (b) and (c), respectively, of Section 17251.
  (b) A self-certifying district shall comply with subdivision (a) by certifying to the State Department of Education and the board that the site selection, and the building plans and specifications, comply with the standards adopted by the department pursuant to subdivisions (b) and (c), respectively, of Section 17251. The self-certifying district shall maintain documentation of the determinations made pursuant to this subdivision as required by the board. Those determinations shall be subject to subsequent audit by the State Department of Education in accordance with this section.
  (c) The State Department of Education shall conduct random audits of the information certified by self-certifying districts pursuant to subdivision (b), using generally accepted auditing principles, at any time to ensure compliance with the law.
  (d) If any information certified by a self-certifying district pursuant to subdivision (b) is found by the department to contain any material inaccuracy, the department shall so notify the board. The board shall thereupon impose both of the following penalties:
  (1) Pursuant to a repayment schedule approved by the board of no more than five years, the district shall repay to the board, for deposit in the State School Building Lease-Purchase Fund, an amount equal to the amount of project funding allocated under this chapter to acquire any site that was selected in material violation of the standards adopted by the department pursuant to subdivision (b) of Section 17251, together with interest at the rate paid on moneys in the Pooled Money Investment Account or at the highest rate of interest for the most recent issue of state general obligation bonds as established pursuant to Chapter 4 (commencing with Section 16720) of Part 3 of Division 4 of Title 2 of the Government Code, whichever is greater. The amount of any repayment owing under this paragraph for any fiscal year, which is not repaid otherwise by the district, shall be withheld by the board from any project funding that otherwise would be allocated to that district under this chapter in that fiscal year. As to any repayment obligation remaining for that fiscal year, the board shall notify the Superintendent of Public Instruction, who shall withhold the amount of that remaining obligation from the apportionments to be made to the district from the State School Fund in that fiscal year.
  (2) The board shall prohibit the district from exercising the self-certifying authority under subdivision (b) under any subsequent applications for project funding for a period of up to five years following the date of the finding of a material inaccuracy, or until the district's repayment of the entire amount owing under paragraph (1), whichever occurs later.
  (e) Any school district against which the board imposed the penalties under paragraphs (1) and (2) of subdivision (d) may submit for binding determination by an arbitrator the issue of whether the penalties imposed are disproportionate to the inaccuracy certified by the district. Except as otherwise provided by this chapter, the procedure governing the arbitration shall be as set forth in Title 9 (commencing with Section 1280) of Part 3 of the Code of Civil Procedure.
  (f) It is the intent of the Legislature that audits as described in this section not interfere with the application and construction process under this chapter unless one or more violations are discovered.
Upon request of any school district, the State Department of Education shall provide assistance in the evaluation and utilization of existing school facilities and the justification of the need for schoolsites, new facilities, and the rehabilitation or replacement of existing facilities, in accordance with board regulations.
(a) The board shall not authorize a contract for the construction of any new school, or for the addition to, or reconstruction or alteration of, any existing building, for lease-purchase to any school district unless the applicant district has submitted plans therefor to the Department of General Services and obtained the written approval of the department pursuant to Article 3 (commencing with Section 17280) of Chapter 3 of Part 10.5.
  (b) The board, or the self-certifying district, as applicable, shall certify the compliance of a project with Sections 17212, 17212.5, and 17213, with Division 13 (commencing with Section 21000) of the Public Resources Code, and with any other law that applies to that project, but may require documentation of compliance only as to requirements that are applicable under this chapter. Notwithstanding any other law, for purposes of Division 13 (commencing with Section 21000) of the Public Resources Code, the applicant district shall be deemed to be the "lead agency" with regard to any project funded for that district under this chapter.
(a) The board shall authorize the applicant school district to act as its agent in the performance of acts specifically approved by the board and all acts required pursuant to Article 3 (commencing with Section 17280) of Chapter 3 of Part 10.5. That authorization shall include, but is not limited to, the selection of schoolsites, the securing of appraisals, the contracting for architectural services, the advertisement for construction bids and the entering into of contracts therefor and the purchase of furniture and equipment.
  (b) If, pursuant to the authority granted under subdivision (a), a self-certifying district submits to the board two or more independent appraisals and certifies to the board that the appraisals were performed by appraisers licensed or certified in accordance with Part 3 (commencing with Section 11300) of Division 4 of the Business and Professions Code and were obtained in accordance with standards and procedures imposed by the board for that purpose, the district shall not be required to document its compliance with those standards and procedures except as specified in Section 17041.2. In addition, the board shall use any of those appraisals, including an appraisal that is not the highest bid appraisal, for the purposes of this section, except that the board may substitute, for the results of those appraisals, the results of one or more independent appraisals, which may include an appraisal performed by the Department of General Services, obtained by the board for that purpose.
  (c) If, pursuant to the authority granted under subdivision (a), any bid reported to the board by a self-certifying district as the lowest responsible bid for a construction contract does not exceed the cost limit established by the board for that purpose, and the district certifies to the board that the bid was obtained in accordance with standards and procedures imposed by the board for that purpose, the district shall not be required to document its compliance with those standards and procedures except as specified in Section 17041.2.
Notwithstanding any other provisions of this chapter, the funding by the board of contracts entered into by a school district pursuant to this chapter shall not, in itself, make the board liable for any tort, breach of contract, or any other action for damages caused by a school district arising from those contracts. These contracts include, but are not limited to, contracts between the school district and its construction contractors, construction managers, architects, or engineers. The school district shall be liable for all torts, breaches of contract, or any other actions for damages caused by the school district.
(a) In expending funds for any project under this chapter, a school district acts as an agent of the state and all sites purchased and improved, all equipment purchased, and all buildings constructed, altered or added to through the expenditure of funds apportioned under this chapter, are declared to be, and are, the property of the state.
  (b) The Director of General Services shall file with the county recorder of the county in which any site purchased or improved through the expenditure of funds under this chapter is located a certificate, properly acknowledged, indicating the state's interest in real property of the district by virtue of this section, without the necessity of particularizing the real property. The recorder shall record and index the certificate in the same manner as abstracts of judgments and the certificate shall constitute constructive notice of the state's interest in the particular real property affected. The certificate shall, as to any party thereafter acquiring real property or any interest therein in the county from the school district, have the same force, effect and priority as if it had been a judgment lien imposed upon real property which was not exempt from execution. That effect shall commence upon recordation and shall continue until the certificate is discharged or released as provided herein.
  (c) Upon request, the Director of General Services shall issue either of the following:
  (1) A release of the state's interest in any real property or a portion thereof that the district has been authorized by the board to dispose of under Section 17039, provided that delivery of such release may be subject to such conditions as may be prescribed by the board to protect the state's interest.
  (2) A disclaimer of the state's interest in any real property or a portion thereof of the district, the disposition of which the board is not required to consent to under the terms of Section 17039, provided that the delivery of such disclaimer may be subject to such conditions as the board deems appropriate to protect the interest of the state, including conditions relating to the amount of consideration to be received from the disposition where the board asserts an interest in the proceeds of such disposition under other provisions of this chapter. The release or disclaimer shall conclusively protect any third party relying upon the same and shall be acknowledged to permit recordation by the county recorder.
  (d) Upon payment by the district of all amounts required to be paid by it, or on its behalf, to the state under this chapter, each of the following shall occur:
  (1) The Director of General Services shall file with the county recorder a release of any certificate, which release shall be recorded and indexed in the same index as the certificate.
  (2) The title to personal property purchased by the school district with funds apportioned under this chapter shall revert thereto without further action by the state.
Notwithstanding any other provision to the contrary, all lease agreements shall terminate 40 years from the date of execution and title to the property covered therein shall revert to the district as though full payment had been made.
Notwithstanding any other provision of this chapter, any project funded under this chapter that involves only the identification, assessment, or abatement of hazardous asbestos in school facilities shall not be subject to Section 17014 or 17032, nor shall that funding cause the transfer to the state of title or any other property interest in the subject facilities.
Notwithstanding any provision to the contrary, no funds authorized by any act for the purpose of this chapter may be expended for any purpose without specific authorization from the board or its designated representatives.
From any moneys in the State School Building Lease-Purchase Fund, the board shall make available to the Director of General Services such amounts as it determines necessary to provide the assistance, pursuant to this chapter, required by Section 15504 of the Government Code.
The applicant district, acting as agent for the state, shall comply with all laws pertaining to the construction, reconstruction, or alteration of, or addition to school buildings.
The board shall fix rents for all projects acquired and may change the rents from time to time as may be needed provided the rents shall not in any year exceed the sum of the following:
  (a) One dollar ($1).
  (b) Any interest earned on funds in the county school lease-purchase fund for the district.
  (c) Any unencumbered bond funds of the district, exclusive of funds that are used by the district to fund a project pursuant to Section 17040.2.
  (d) The net proceeds from the sale or lease of any school buildings or land no longer needed for school purposes, exclusive of proceeds that are used for capital outlay expenditures for school construction that conforms to building area standards established under this chapter, for revenue purposes under a joint venture as authorized by Section 17032.3.
(a) Any school district for which one or more projects has been funded under this chapter may, pursuant to written agreement with any other public or private person or entity, utilize any school buildings, land, or other real property interest that the governing board determines is not needed for school purposes, and will not be needed for school purposes within the next 30 years, in a joint venture with that person or entity to generate revenues for school facilities purposes, pursuant to the following conditions:
  (1) The district has developed a school district asset utilization plan, setting forth the information required under subdivision (b), which plan has been the subject of a public hearing, and the governing board of the district has made the finding that the implementation of the plan will benefit the district.
  (2) Prior to the execution by the school district governing board of any agreement regarding the utilization of the school buildings or land, or both, under a joint venture pursuant to this section, the school district asset utilization plan has been submitted for, and has received, the review and approval of the State Allocation Board. No later than 90 days after the receipt of the plan, the board shall determine whether to approve the plan, which approval shall be granted if the board finds the plan to comply with this section.
  (3) Once every three years after the approval of any plan pursuant to paragraph (2), the school district shall update the plan with information regarding the disposition of the revenues received by the district from the utilization of the school buildings or land, or both, under the joint venture, including the effect of those revenues upon the school facility needs for which the district may otherwise be eligible under this chapter or under any other school facilities program administered by the board, together with such other information as the board may require, and shall resubmit the plan to the board for its review and approval. In the event that the board refuses to approve the plan on the basis that the district is no longer in substantial compliance with this section, the surplus school buildings or land, or both, utilized under the joint venture shall no longer be exempt from the rental requirements of Section 17032.
  (4) Pursuant to a school district asset utilization plan approved under this section, the school district may utilize school buildings or land, or both, in a joint venture, the revenues from which shall be placed by the district in a separate fund. The principal and interest from that separate fund may be expended by the district only for the following school facilities purposes, as authorized under the approved plan, in accordance with the pupil loading and cost standards established pursuant to this chapter: the acquisition of land, new construction, reconstruction, modernization, rehabilitation, and deferred maintenance.
  (b) For purposes of this section, a school district asset utilization plan shall include, but not necessarily be limited to, all of the following:
  (1) A specific description of the surplus school buildings or land, or both, to be utilized under the joint venture.
  (2) The identification of the current educational uses of the surplus school buildings or land, or both, and of the educational uses proposed under the joint venture.
  (3) The identification of the current noneducational uses of the surplus school buildings or land, or both, and of the noneducational uses proposed under the joint venture, and a specific assessment of the compatibility of those uses with any applicable general or specific governmental land use plans and with applicable zoning restrictions.
  (4) A description of the prospective economic benefits to be derived by the district from the joint venture.
  (5) A description of the prospective educational benefits to be derived by the district from the joint venture.
  (6) A comprehensive description of the joint venture, including, but not limited to, a description of the intended means of financing the joint venture.
  (7) A plan for the disposition of the revenues received by the district from the joint venture.
(a) The board shall establish the annual rent and conditions to be met by the lessee of a portable classroom leased pursuant to Section 17717.2 and shall require lessees to undertake all necessary maintenance, repairs, renewals, and replacements to ensure that a project is at all times kept in good repair, working order, and condition. All costs incurred for this purpose shall be borne by the lessee.
  (b) For purposes of this section, "good repair" has the same meaning as specified in subdivision (d) of Section 17002.
Rent, charges, and fees collected in error may be refunded by the board in accordance with regulations prescribed by the board.
A county school lease-purchase fund is hereby created in the county treasury within each county for each school district project in the county.
The board may from time to time authorize the Controller to transfer any funds that the board may deem necessary from the State School Building Lease-Purchase Fund established for a given project to the corresponding county school lease-purchase fund in the county treasury.
(a) Except as provided in subdivision (b), funds may be expended from the county school lease-purchase fund by the applicant school district only when specifically authorized by the board for either direct project costs or reimbursements.
  (b) Upon specific authorization by the board, applicant school districts may be reimbursed from the county school lease-purchase fund for expenditures, or commitments therefor, made prior to the approval of a project by the board, subject to all of the following conditions:
  (1) The expenditures or commitments were made in accordance with the terms of the approval of a project.
  (2) The expenditures or commitments were made not more than four years prior to the approval of a project.
  (3) The expenditures or commitments do not include any cost incurred for construction of a project.
The board shall require school districts to insure at their own expense for the benefit of the state, all sites, equipment and buildings which are, under Section 17030, the property of the state, against such risks and in such amounts as the board may deem necessary to protect the interests of the state. No project funds shall be used to pay the premiums on such insurance. All payments resulting from claims made against said insurance shall be made payable to and retained by the board. Funds so received shall be utilized by the board for repair or replacement of the facilities for which claim was made. In no event may the amounts expended from such funds for such repair or replacement exceed the payments received.
(a) Not more than one hundred fifty million dollars ($150,000,000) of the moneys authorized by the State School Building Lease-Purchase Bond Law of 1982 (Sec. 34, Ch. 552, Stats. 1995) shall be reserved for the reconstruction or modernization of facilities within the meaning of this chapter.
  (b) For purposes of this section, the State Allocation Board shall establish a separate priority system which shall be based on the following factors and any other factors which the board determines are appropriate:
  (1) Structural condition and age of the building.
  (2) Percentage of pupils affected in the district or attendance area.
  (3) Degree of utilization of eligible buildings.
  (4) Other building code deficiencies, such as health, safety, or electrical problems.
Not more than two hundred million dollars ($200,000,000) of the moneys authorized by the State School Building Lease-Purchase Bond Law of 1982 (Sec. 34, Ch. 552, Stats. 1995) shall be reserved for the reconstruction or modernization of facilities within the meaning of this chapter.
Of the moneys reserved for the rehabilitation or modernization of facilities pursuant to Section 17039.1, the board may reserve not more than twenty-five million dollars ($25,000,000) for apportionments to school districts that the board has determined to be in severe need of the apportionment. In addition, of the moneys reserved for the reconstruction or modernization of facilities pursuant to Section 17696.96 of the Greene-Hughes School Building Lease-Purchase Bond Law of 1986 (Sec. 34, Ch. 552, Stats. 1995), the board may reserve up to and including 10 percent for this purpose. In either event, the apportionment shall be for purposes of site acquisition and the construction of school facilities for schoolsites that meet one or more of the conditions established by the board, which shall include, but are not limited to, the following:
  (a) The schoolsite is not less than 30 years of age.
  (b) The schoolsite has accommodated a significant increase in enrollment during the last 10-year period.
  (c) Enrollment increases have been accommodated by placing relocatable structures on the schoolsite without expanding the schoolsite.
  (d) The schoolsite has inadequate playground space for its enrollment.
  (e) The schoolsite has inadequate meal facilities, and those facilities are used for more than three times the number of pupils for which the facilities were originally designed.