25135.6
. (a) A county shall prepare, review, and adopt the county
hazardous waste management plan pursuant to the schedule specified in
this section.
(b) On or before December 31, 1987, each county, with the
cooperation of affected local jurisdictions and the advisory
committee established pursuant to Section 25135.2, shall prepare a
draft county hazardous waste management plan and submit the draft
plan to the department. If a county shows to the department that the
county has made substantial compliance towards completing the draft
county hazardous waste management plan and needs additional time to
complete the draft plan, the department may extend to March 31, 1988,
the date by which the draft plan is required to be submitted. The
county shall involve the public with the preparation of the draft
plan, to the fullest extent possible, by public hearings,
informational meetings, and other appropriate forums that offer the
public the opportunity to respond to clearly defined alternative
objectives, policies, and actions.
(c) On or before March 31, 1988, or, if the department has given
the county a time extension pursuant to subdivision (b), on or before
June 30, 1988, the county shall conduct hearings on the draft county
hazardous waste management plan, in the number determined
appropriate by the county. The county shall provide affected local
jurisdictions, the public, industry, business organizations, and the
hazardous waste management industry with the full opportunity to
comment orally and in writing on the draft county hazardous waste
management plan.
(d) On or before March 31, 1988, or, if the department has given
the county a time extension pursuant to subdivision (b), on or before
June 30, 1988, the department shall review the draft plan, and
provide each county with comments which specify the changes or
additions which are required to be made to the draft plan to result
in a final plan which can be approved by the department pursuant to
Section 25135.7.
(e) After conducting the review and comment period required by
subdivision (c), each county shall revise, as appropriate, the draft
county hazardous waste management plan.
(f) The revised county hazardous waste management plan shall be
approved by a majority of the cities within the county which contain
a majority of the population of the incorporated area of the county,
subject to subdivision (g).
(g) The revised county hazardous waste management plan shall be
submitted to each city within the county for their approval. Each
city shall act upon the revised county hazardous waste management
plan within 90 days after the city has received the plan. If a city
fails to act upon the plan within 90 days of receiving the plan, the
city shall be deemed to have approved the plan as submitted.
(h) On or before September 30, 1988, or, on or before May 31,
1989, if the county is given an extension pursuant to subdivision (a)
of Section 25135.7, the county shall adopt the revised county
hazardous waste management plan as the final county hazardous waste
management plan. If the county is given an additional time extension
to September 1, 1989, pursuant to subdivision (a) of Section 25135.
7, the county shall adopt the revised county hazardous waste
management plan as the final county hazardous waste management plan
by August 31, 1989.