Section 25135.7.5 Of Article 3.5. Hazardous Waste Management Plans From California Health And Safety Code >> Division 20. >> Chapter 6.5. >> Article 3.5.
25135.7.5
. (a) If the department disapproves a county hazardous
waste management plan pursuant to subdivision (a) of Section 25135.7,
or a regional hazardous waste management plan pursuant to Section
25135.3, the department shall provide the county or regional council
of governments, in writing and at the time of disapproval, with a
detailed description of its reasons for disapproval of the plan. A
county or regional council of governments with a disapproved
hazardous waste management plan may submit a revised plan to the
department one time only. A revised county or regional hazardous
waste management plan shall be submitted to the department within 270
days of the effective date of the act adding this section, or within
270 days of plan disapproval if the plan is disapproved by the
department after the effective date of the act adding this section. A
county or regional council of governments shall notify the
department of their intent to revise and resubmit a disapproved plan
within 45 days of the effective date of the act adding this section,
or within 45 days of plan disapproval, if the plan is disapproved
after the effective date of the act adding this section. A
resubmitted county or regional plan shall contain detailed responses
to all of the reasons for disapproval of the plan described by the
department. The department shall provide counties with informational
guidelines on developing an approvable plan.
(b) Before submitting a revised county hazardous waste management
plan to the department pursuant to this section, the revised plan
shall be approved by a majority of the cities within the county which
contain a majority of the population of the incorporated area of the
county, as specified in subdivisions (f) and (g) of Section 25135.6.
A city which fails to act upon a county plan revised pursuant to
this section within 90 days after the plan has been submitted to the
city by the county shall be deemed to have approved the revised plan.
(c) The department shall review and either approve or disapprove a
county or regional hazardous waste management plan revised pursuant
to subdivision (a) within 180 days of receiving the revised plan.
(1) The department shall approve a revised county hazardous waste
management plan if the department makes all of the determinations in
paragraphs (1), (2), (3), and (4) of subdivision (a) of Section
25135.7. If the department approves a revised county hazardous waste
management plan pursuant to this section, the county shall comply
with subdivision (b) of Section 25135.7, and each city within that
county shall comply with subdivision (c) of Section 25135.7.
(2) The department shall approve a revised regional hazardous
waste management plan if the department makes all of the
determinations in subdivision (g) of Section 25135.3.
(d) A county which did not submit its plan to the department
within the due dates for plan submittal established by subdivision
(a) of Section 25135.7, or a county whose plan was not formally acted
upon by the department by the February 28, 1990, deadline, may
submit their plan to the department for review and approval or
disapproval pursuant to the provisions governing the resubmittal of
revised plans established by this section.
(e) A council of governments which did not submit its plan to the
department within the due dates for plan submittal established by
Section 25135.3, or whose plan has not been formally acted upon by
the department, may submit their plan to the department for review
and approval or disapproval pursuant to the provisions governing the
resubmittal of revised plans established by this section.