Section 25200.7.5 Of Article 9. Permitting Of Facilities From California Health And Safety Code >> Division 20. >> Chapter 6.5. >> Article 9.
25200.7.5
. (a) On or before December 31, 2015, the department shall
issue a final permit decision on an application for a hazardous
waste facilities permit submitted to the department by a facility
operating under a grant of interim status pursuant to Section 25200.5
on or before January 1, 1986, by either issuing a final permit
pursuant to the application or a final denial of application.
(b) Interim status granted pursuant to Section 25200.5 for a
facility described in subdivision (a) shall terminate on December 31,
2015, or on the date on which the department issues a final permit
decision on the application for a hazardous waste facilities permit,
whichever is earlier. If a person petitions the department for review
of a final permit decision to approve a hazardous waste facilities
permit or a facility currently operating under interim status, then
the interim status shall not terminate until final administrative
disposition of the petition, even if the final administrative
disposition occurs after December 31, 2015.
(c) Except as provided in subdivision (b), interim status granted
for a facility before January 1, 2015, shall terminate on January 1,
2020, or on the date on which the department issues a final permit
decision on the application for a hazardous waste facilities permit,
whichever is earlier.
(d) Interim status granted for a facility on or after January 1,
2015, shall terminate five years from the date on which the interim
status is granted or on the date on which the department issues a
final permit decision on the application for a hazardous waste
facilities permit, whichever is earlier.