Section 6974 Of Chapter 6.7. Construction Manager/general Contractor Method: Regional Projects On Expressways From California Public Contract Code >> Division 2. >> Part 1. >> Chapter 6.7.

6974
. (a) Upon completion of a project using the Construction Manager/General Contractor method, the regional transportation agency shall prepare a progress report to its governing body. The progress report shall include, but not be limited to, all of the following information:
  (1) A description of the project.
  (2) The name of the entity that was awarded the project.
  (3) The estimated and actual costs of the project.
  (4) The estimated and actual schedule for project completion.
  (5) A description of any written protests concerning any aspect of the solicitation, bid, proposal, or award of the project, including, but not limited to, the resolution of the protests.
  (6) An assessment of the prequalification process and criteria required by this chapter.
  (7) A description of the method used to evaluate the bid or proposal, including the weighting of each factor and an assessment of the impact of this requirement on a project.
  (8) A description of any challenges or unexpected problems that arose during the construction of the project and a description of the solutions that were considered and ultimately implemented to address those challenges and problems.
  (9) Recommendations to improve the Construction Manager/General Contractor method authorized by this chapter.
  (b) The progress report shall be made available on the regional transportation agency's Internet Web site.