Section 130064 Of Article 9. Hospital Owner Responsibilities From California Health And Safety Code >> Division 107. >> Part 7. >> Chapter 1. >> Article 9.
130064
. (a) In lieu of the extension described in subdivision (f)
of Section 130060, the office may grant an extension to a general
acute care hospital pursuant to either subdivision (c) or (f) if the
hospital building will not meet the seismic safety standards of that
section by January 1, 2013, due to a local planning delay.
(b) When applying for an extension under this section, the owner
of the general acute care hospital shall submit to the office
documentation that includes at least all of the following:
(1) The original schedule of the project or projects as had been
originally anticipated.
(2) The schedule of the project or projects as currently
projected.
(3) A timeline for the submission of documents to the local
planning authority or jurisdiction.
(4) Documentation that the local planning authority for the
project and for the enabling phases of the project does not grant
approvals prior to November 1, 2010, where the hospital had
originally filed the local application prior to January 1, 2008.
(5) A proposed construction timeframe demonstrating the completion
of the project once the permit is issued. The construction timeframe
shall be approved by the office and shall only include the amount of
time that is reasonably necessary to complete the construction
required to meet the seismic safety requirements.
(c) The office may grant an extension, in full one-year
increments, but no longer than three consecutive years, that
compensates for delays determined pursuant to subdivision (d).
(d) The office shall conduct a comprehensive review of the
schedule for the project or projects according to criteria specified
in this section. This review shall encompass the project or projects
under the jurisdiction of the office, as well as other project phases
not under the jurisdiction of the office. The office shall consider
the cumulative effect of local approval timelines for all elements of
the project or projects, inclusive of changes in scope or sequence
of the project or projects required by the local planning process.
The office may grant extensions based on an evaluation of each of the
following circumstances:
(1) Where the local planning authority approvals have delayed or
will delay the construction start date of the project or projects.
(2) Where the local conditions of approval on a project or
projects extend the duration beyond the originally anticipated
construction completion date.
(3) Where the cumulative effect of delays on the project or
projects creates additional construction delays due to local seasonal
weather impact requirements of the local planning authority.
(4) Construction related to the seismic retrofit or replacement
project has begun by January 1, 2013.
(5) The project or projects were submitted for review by the
department no later than January 1, 2009.
(6) The project or projects have received a building permit from
the department no later than January 1, 2012.
(e) Every six months after the approval of the extension, the
hospital owner shall report to the office on the status of the
project or projects, demonstrating that it is making reasonable
progress toward meeting the construction timeline.
(f) The office may grant an additional extension of up to two
years in addition to the extension granted pursuant to subdivisions
(c) and (d) only if the project or projects meet all of the following
criteria:
(1) A matrix of buildings at the hospital that identifies
compliance of each building to the standards required by Section
130065 at the completion of the project or projects.
(2) The construction timelines submitted pursuant to subdivision
(a) were determined to go beyond three years from the date the
building permit was issued.
(3) Acute care services will not be provided in any SPC-1 building
at any time during the extension.
(4) The hospital demonstrates that it has, and maintains
throughout the extension, life safety systems in all acute care
patient care areas that do not depend on, and are not routed through,
an SPC-1 building.
(5) The hospital either demonstrates that the SPC-1 building does
not pose a structural risk to an adjoining hospital building that is
used for acute care services or mitigates the risk in accordance with
a deadline described in subdivision (f) of Section 130060 that the
office determines will best protect patient safety.
(g) The office may revoke an extension granted pursuant to this
section for any hospital building where the work of construction is
abandoned or suspended for a period of at least six months, unless
the hospital demonstrates that the abandonment or suspension was
caused by factors beyond its control.
(h) The office may revoke an extension granted pursuant to this
section if it is determined that any information submitted pursuant
to this section was falsified in any manner by the hospital or if the
hospital fails to meet any of the criteria or conditions specified
in this section.
(i) Regulatory submissions made by the office to the California
Building Standards Commission pursuant to this section shall be
deemed, and shall be adopted as, emergency regulations.
(j) The hospital owner that applies for an extension pursuant to
this section shall pay to the office an additional fee, to be
determined by the office, sufficient to cover the additional cost
incurred by the office for maintaining all reporting requirements
established under this section, including, but not limited to, the
costs of reviewing and verifying the extension documentation
submitted pursuant to this section. This additional fee shall not
include any cost for review of the plans or other duties related to
receiving a building or occupancy permit.
(k) A hospital denied an extension pursuant to this section may
appeal the denial to the Hospital Building Safety Board.