Section 10261 Of Article 8. Modifications; Performance; Payment From California Public Contract Code >> Division 2. >> Part 2. >> Chapter 1. >> Article 8.
10261
. (a) Payments upon contracts shall be made as the department
prescribes upon estimates made and approved by the department, but
progress payments shall not be made in excess of 100 percent of the
percentage of actual work completed plus a like percentage of the
value of material delivered on the ground or stored subject to or
under the control of the state, and unused, except as otherwise
provided in this section. The department shall withhold not more than
5 percent of the contract price until final completion and
acceptance of the project. However, at any time after 95 percent of
the work has been completed, the department may reduce the funds
withheld to an amount not less than 125 percent of the estimated
value of the work yet to be completed, as determined by the
department, if the reduction has been approved, in writing, by the
surety on the performance bond and by the surety on the payment bond.
The Controller shall draw his or her warrants upon estimates so made
and approved by the department and the Treasurer shall pay them. The
funds may be released by electronic transfer if that procedure is
requested by the contractor, in writing, and if the department has,
in place at the time of the request, the mechanism for the transfer.
(b) (1) Notwithstanding subdivision (a), when the director of the
department has made a finding prior to the bid that a specified
project is substantially complex and therefore requires a higher
retention amount than 5 percent, and the department includes in the
bid documents details explaining the basis for the finding and the
actual retention amount, then payments upon contracts by the
department shall be made as the department prescribes upon estimates
made and approved by the department. However, progress payments shall
not be made in excess of 95 percent of the percentage of actual work
completed, plus a like percentage of the value of material delivered
on the ground or stored, subject to, or under the control of the
state, and unused, except as otherwise provided in this section. At
any time after 95 percent of the work has been completed, the
department may reduce the funds withheld to an amount not less than
125 percent of the estimated value of the work yet to be completed,
as determined by the department, if the reduction has been approved,
in writing, by the surety on the performance bond and by the surety
on the payment bond. The Controller shall draw his or her warrants
upon estimates so made and approved by the department and the
Treasurer shall pay them with funds appropriated therefor. The funds
may be released by electronic transfer if that procedure is requested
by the contractor, in writing, and if the department has, in place
at the time of the request, the mechanism for the transfer.
(2) Any finding by the director of a department that a project is
substantially complex shall include a description of the specific
project and why it is a unique project that is not regularly,
customarily, or routinely performed by the agency or licensed
contractors.
(c) This section shall remain in effect only until January 1,
2018, and as of that date is repealed, unless a later enacted
statute, that is enacted before January 1, 2018, deletes or extends
that date.