Section 10346 Of Article 4. Contracts For Services From California Public Contract Code >> Division 2. >> Part 2. >> Chapter 2. >> Article 4.
10346
. Contracts may provide for progress payments to contractors
for work performed or costs incurred in the performance of the
contract. Not less than 10 percent of the contract amount shall be
withheld pending final completion of the contract. However, if the
contract consists of the performance of separate and distinct tasks,
then any funds so withheld with regard to a particular task may be
paid upon completion of that task.
No state agency shall make progress payments on a contract unless
it first has established procedures, approved by the department,
which will ensure that the work or services contracted are being
delivered in accordance with the contract.