Section 10826 Of Article 7. Contract Requirements From California Public Contract Code >> Division 2. >> Part 2. >> Chapter 2.5. >> Article 7.
10826
. Every contract shall contain a provision in regard to the
time when the whole or any specified portion of the work contemplated
shall be completed, and shall provide that for each day completion
is delayed beyond the specified time, the contractor shall forfeit
and pay to the state a specified sum of money, to be deducted from
any payments due or to become due to the contractor. The sum so
specified is valid as liquidated damages unless manifestly
unreasonable under the circumstances existing at the time the
contract was made. A contract for a road project may also provide for
the payment of extra compensation to the contractor, as a bonus for
completion prior to the specified time, such provision, if used, to
be included in the specifications and to clearly set forth the basis
for such payment.