Section 20436 Of Article 27. Legislative Bodies—improvement Act Of 1911 From California Public Contract Code >> Division 2. >> Part 3. >> Chapter 1. >> Article 27.
20436
. If an action is commenced under the provisions of this
chapter to determine the validity of any contract or proposed
contract, and the contract has not been signed, the contractor shall
not be obligated to sign the same until a judgment sustaining the
validity of the proceedings and the proposed contract has become
final. If the contractor has signed and executed the contract, he
shall not be obligated to begin work until a judgment sustaining the
validity of the proceedings and the contract has become final. If a
judgment is entered holding the contract invalid, the contractor
shall be discharged and relieved of all obligation under the
contract, and he and his sureties shall be discharged and relieved of
all obligation upon any bond required by law in connection with such
contract.