20894
. If the contractor abandons the work, or fails to proceed
with it as rapidly as required by the contract, the city forester may
relet the work in the same manner as in the first letting, or
complete or cause it to be completed in any other manner he or she
deems advisable. The city forester may retain the amount of any
expense incidental to the reletting, out of any funds due or to
become due to the contractor, and may also hold the contractor and
the sureties upon the contractor's bond responsible for any
additional expenses and for any damages resulting from the
abandonment or failure to complete the contract.