Section 21009 Of Article 68. Drainage Districts From California Public Contract Code >> Division 2. >> Part 3. >> Chapter 1.5. >> Article 68.
21009
. If the contractor shall fail to begin in good faith the work
provided for in said contract within the time in said contract set
forth, or shall fail thereafter to prosecute said work in a
workmanlike and diligent manner, or shall fail in any other respect
to carry out the terms of said contract, then the board of
supervisors shall cause written notice to be served upon said
contractor, specifying the particular areas in which he or she is not
fulfilling the requirements of said contract, and if for a period of
three days thereafter said contractor shall fail to remedy the
defects set forth in said notice, and to prosecute said work
thereafter with diligence and in a workmanlike manner, then the board
of supervisors shall either take over said contract and complete
said work, or shall relet said contract, without the necessity of
advertising for bids, and cause the work to be completed, and shall
declare the bond given by said contractor forfeited and order suit
brought thereon, and all moneys collected therefrom shall be paid
into the interest and sinking fund of the district.