Section 21152 Of Article 82. Alameda County Flood Control And Water Conservation District From California Public Contract Code >> Division 2. >> Part 3. >> Chapter 1.5. >> Article 82.
21152
. If any change or addition in the work being performed under
a construction contract pursuant to this section is deemed necessary,
the board may authorize the contractor to proceed with the change or
addition without the formality of obtaining bids therefor, provided
that the extra cost to the district shall not exceed five thousand
dollars ($5,000) when the total amount of the original contract does
not exceed fifty thousand dollars ($50,000), nor 10 percent of the
amount of any original contract which exceeds fifty thousand dollars
($50,000). The board may, by board order, authorize the Director of
Public Works or other district officer to order such changes or
additions in the work being performed, provided that the above
conditions are satisfied and that the cost of the change or addition
does not exceed twenty-five thousand dollars ($25,000). The
authorization to the Director of Public Works or other district
officer shall include the authority to grant any contract time
extensions necessary in connection with the changes or additions. All
changes or additions to the work shall be ordered in writing. If a
change or addition in a contract awarded under the provisions of this
section is requested by any person, firm, corporation, or public
agency, other than the district, which person, firm, corporation, or
public agency agrees to pay all of the cost of the change or
addition, the board may, by board order, authorize the Director of
Public Works or other district officer to direct the contractor to
proceed with the change or addition without the formality of
obtaining bids therefor, provided that the cost of the change or
addition does not exceed 15 percent of the original contract price.