Section 4106 Of Chapter 4. Subletting And Subcontracting From California Public Contract Code >> Division 2. >> Part 1. >> Chapter 4.
4106
. If a prime contractor fails to specify a subcontractor or if
a prime contractor specifies more than one subcontractor for the same
portion of work to be performed under the contract in excess of
one-half of 1 percent of the prime contractor's total bid, the prime
contractor agrees that he or she is fully qualified to perform that
portion himself or herself, and that the prime contractor shall
perform that portion himself or herself.
If after award of contract, the prime contractor subcontracts,
except as provided for in Sections 4107 or 4109, any such portion of
the work, the prime contractor shall be subject to the penalties
named in Section 4111.