Section 6701 Of Chapter 6.3. Construction Manager/general Contractor Authority: Department Of Transportation From California Public Contract Code >> Division 2. >> Part 1. >> Chapter 6.3.

6701
. (a) The Construction Manager/General Contractor method provided by this chapter may be used by the department, but is not limited to, when it is anticipated that it will reduce project costs or expedite project completion in a manner that is not achievable through the design-bid-build method. Notwithstanding any other law, for projects utilizing the Construction Manager/General Contractor method provided by this chapter, the department shall advertise, award, and administer the Construction Manager/General Contractor contract. The department shall not delegate the contracting authority.
  (b) The department may use the Construction Manager/General Contractor method on no more than six projects, at least five of which shall have construction costs greater than ten million dollars ($10,000,000).
  (c) On at least four of the projects utilizing the Construction Manager/General Contractor method provided by this chapter, the department shall use department employees or consultants under contract with the department to perform all project design and engineering services related to design required for Construction Manager/General Contractor project delivery consistent with Article XXII of the California Constitution. On all six projects, the department shall use department employees or consultants under contract with the department to perform all construction inspection services required for Construction Manager/General Contractor project delivery consistent with Article XXII of the California Constitution. Department resources, including personnel requirements, necessary to perform all services described in this subdivision shall be included in the department's capital outlay support program for workload purposes in the annual Budget Act.
  (d) (1) The department shall prepare and submit to the Legislature, no later than July 1 of each year during which any project using the Construction Manager/General Contractor method is ongoing, a report that describes each project and provides relevant data, including, but not limited to, the stage of completion, district, cost, description, status, and estimated time to completion.
  (2) The department shall prepare and submit to the Legislature, no later than July 1 of the year after any project using the Construction Manager/General Contractor method has been completed, a report that includes, in addition to the data in paragraph (1), all of the following:
  (A) Data on initial cost estimates, actual cost upon completion, and the reasons for any difference.
  (B) Estimated time for completion, actual time of completion, and the reasons for any difference.
  (C) The number and dollar value of any change orders for all projects completed using the Construction Manager/General Contractor method.
  (e) (1) A report to be submitted pursuant to subdivision (d) shall be submitted in compliance with Section 9795 of the Government Code.
  (2) Notwithstanding Section 10231.5 of the Government Code, the requirement for submitting a report imposed under subdivision (d) is inoperative on July 1 of the year following the submission of the final report upon completion of the fourth project of the department that uses the Construction Manager/General Contractor method.