Section 130292 Of Article 4. Smart Freeway Corridor Telecommunications Demonstration Projects From California Public Utilities Code >> Division 12. >> Chapter 4. >> Article 4.
130292
. (a) The project shall be coordinated by the statutorily
created county transportation commission in whose jurisdiction the
project is located. The county transportation commission shall
consult with local traffic and law enforcement agencies, the
Department of Transportation, and the Department of the California
Highway Patrol on all aspects of the project in order to provide
necessary coordination of the project with existing plans and
programs.
(b) The county transportation commission shall make preliminary
and final results of the demonstration project available to state and
local public agencies for possible application throughout the state.
(c) The county transportation commission shall prepare and
transmit to the Legislature, no later than one year after the
completion of the project, a report of its findings, conclusions, and
recommendations.
(d) The Department of Transportation shall reimburse the county
transportation commission, from funds appropriated for projects
pursuant to this article, for the costs incurred by the commission
under this article.
(e) No money from the General Fund shall be used for the operation
of a smart freeway corridor telecommunications project established
as a demonstration project pursuant to this article after the
demonstration project is completed.