Section 185033.5 Of Chapter 3. Responsibilities Of The Authority From California Public Utilities Code >> Division 19.5. >> Chapter 3.
185033.5
. On or before March 1, 2017, and every two years
thereafter, the authority shall provide a project update report,
approved by the Secretary of Transportation as consistent with the
criteria in this section, to the budget committees and the
appropriate policy committees of both houses of the Legislature, on
the development and implementation of intercity high-speed train
service pursuant to Section 185030. The report, at a minimum, shall
include a programwide summary, as well as details by project segment,
with all information necessary to clearly describe the status of the
project, including, but not limited to, all of the following:
(a) A summary describing the overall progress of the project.
(b) The baseline budget for all project phase costs, by segment or
contract, beginning with the California High-Speed Rail Program
Revised 2012 Business Plan.
(c) The current and projected budget, by segment or contract, for
all project phase costs.
(d) Expenditures to date, by segment or contract, for all project
phase costs.
(e) A comparison of the current and projected work schedule and
the baseline schedule contained in the California High-Speed Rail
Program Revised 2012 Business Plan.
(f) A summary of milestones achieved during the prior two-year
period and milestones expected to be reached in the coming two-year
period.
(g) Any issues identified during the prior two-year period and
actions taken to address those issues.
(h) A thorough discussion of risks to the project and steps taken
to mitigate those risks.