2812
. Upon application of a private energy producer, and after
notice to any affected public utility and hearing thereon, the
commission shall authorize such producer to construct an
interconnection for the purpose of transporting natural gas, if the
commission finds: (1) that such interconnection is in the public
interest and for the general public benefit, (2) involves natural gas
located within this state in the service area of the public utility,
ultimately consumed within this state, and which would otherwise be
undeveloped because a public utility is unable or unwilling to
purchase it at a price the commission finds to be reasonable, (3)
would not cause energy which would likely otherwise be made available
to the general public to be diverted to the private energy producer,
and (4) that the energy has substantially the equivalent quality and
characteristics as the energy in the utility's transmission system
with which the interconnection would be made. The commission shall
prescribe such reasonable terms, conditions, and requirements as it
deems appropriate.