Section 9600 Of Division 4.9. Restructuring Of Publicly Owned Electric Utilities In Connection With The Restructuring Of The Electrical Services Industry From California Public Utilities Code >> Division 4.9.
9600
. (a) It is the intent of the Legislature that California's
local publicly owned electric utilities and electric corporations
should commit control of their transmission facilities to the
Independent System Operator as described in Chapter 2.3 (commencing
with Section 330) of Part 1 of Division 1. These utilities should
jointly advocate to the Federal Energy Regulatory Commission a
pricing methodology for the Independent System Operator that results
in an equitable return on capital investment in transmission
facilities for all Independent System Operator participants and is
based on the following principles:
(1) Utility specific access charge rates as proposed in Docket No.
EC96-19-000 as finally approved by the Federal Energy Regulatory
Commission reflecting the costs of that utility's transmission
facilities shall go into effect on the first day of the Independent
System Operator operation. The utility specific rates shall honor all
of the terms and conditions of existing transmission service
contracts and shall recognize any wheeling revenues of existing
transmission service arrangements to the transmission owner.
(2) (A) No later than two years after the initial operation of the
Independent System Operator, the Independent System Operator shall
recommend for adoption by the Federal Energy Regulatory Commission a
rate methodology determined by a decision of the Independent System
Operator governing board, provided that the decision shall be based
on principles approved by the governing board including, but not
limited to, an equitable balance of costs and benefits, and shall
define the transmission facility costs, if any, which shall be rolled
in to the transmission service rate and spread equally among all
Independent System Operator transmission users, and those
transmission facility costs, if any, which should be specifically
assigned to a specific utility's service area.
(B) If there is no governing board decision, the rate methodology
shall be determined following a decision by the alternative dispute
resolution method set forth in the Independent System Operator
bylaws.
(C) If no alternative dispute resolution decision is rendered,
then a default rate methodology shall be a uniform regional
transmission access charge and a utility specific local transmission
access charge, provided that the default rate methodology shall be
recommended for implementation upon termination of the cost recovery
plan set forth in Section 368 or no later than two years after the
initial operation of the Independent System Operator, whichever is
later. For purposes of this paragraph, regional transmission
facilities are defined to be transmission facilities operating at or
above 230 kilovolts plus an appropriate percentage of transmission
facilities operating below 230 kilovolts; all other transmission
facilities shall be considered local. The appropriate percentage of
transmission facilities described above shall be consistent with the
guidelines in Federal Energy Regulatory Commission Order No. 888 and
any exception approved by that commission.
(3) If the rate methodology implemented as a result of a decision
by the Independent System Operator governing board or resulting from
the independent system operator alternative dispute resolution
process results in rates different than those in effect prior to the
decision for any transmission facility owner, the amount of any
differences between the new rates and the prior rates shall be
recorded in a tracking account to be recovered from customers and
paid to the appropriate transmission owners by the transmission
facility owner after termination of the cost recovery plan set forth
in Section 368. The recovery and payments shall be based on an
amortization period not to exceed three years in the case of the
electrical corporations or five years in the case of the local
publicly owned electric utilities.
(4) The costs of transmission facilities placed in service after
the date of initial implementation of the Independent System Operator
shall be recovered using the rate methodology in effect at the time
the facilities go into operation.
(5) The electrical corporations and the local publicly owned
electric utilities shall jointly develop language for implementation
proposals to the Federal Energy Regulatory Commission based on these
principles.
(6) Nothing in this section shall compel any party to violate
restrictions applicable to facilities financed with tax-exempt bonds
or contractual restrictions and covenants regarding use of
transmission facilities existing as of December 20, 1995.
(b) Following a final Federal Energy Regulatory Commission
decision approving the Independent System Operator, no California
electrical corporation or local publicly owned electric utility shall
be authorized to collect any competition transition charge
authorized pursuant to this division and Chapter 2.3 (commencing with
Section 330) of Part 1 of Division 1 unless it commits control of
its transmission facilities to the Independent System Operator.