Section 30952.2 Of Chapter 4.3. Metropolitan Transportation Commission From California Streets And Highways Code >> Division 17. >> Chapter 4.3.
30952.2
. (a) The department shall provide monthly reports to the
Toll Bridge Program Oversight Committee, including, but not limited
to, the construction status, actual expenditures, and forecasted
costs and schedules for the Benicia-Martinez Bridge construction
project and the state toll bridge seismic retrofit program projects.
(b) (1) Commencing August 15, 2005, and quarterly thereafter until
completion of all applicable projects, the Toll Bridge Program
Oversight Committee shall provide quarterly reports within 45 days of
the end of each quarter to the transportation and fiscal committees
of both houses of the Legislature and the California Transportation
Commission for the toll bridge seismic retrofit program in
subdivision (a) of Section 188.5.
(2) The report shall include details of each toll bridge seismic
retrofit project and all information necessary to clearly describe
the status of the project, including, but not limited to, all of the
following:
(A) A progress report.
(B) The baseline budget for capital and capital outlay support
costs for the revised program cost estimate, as described in Section
188.6.
(C) The current or projected budget for capital and capital outlay
support costs.
(D) Expenditures to date for capital and capital outlay support
costs.
(E) A comparison of the current or projected schedule and the
baseline schedule that was assumed.
(F) A summary of milestones achieved during the quarterly period
and any issues identified and actions taken to address those issues.
(G) A summary of the expenses incurred by the Toll Bridge Program
Oversight Committee to perform the duties required by Sections
30952.05 and 30952.1.
(H) A summary of the incentives, disincentives, and criteria for
each utilized by the department, and the expenses incurred by the
department, pursuant to Section 30952.3.
(3) The report described in paragraph (1) shall also include a
programwide summary of the program's budget status for capital and
capital outlay support costs.