Section 31475 Of Chapter 7. Otay Mesa East Toll Facility Act From California Streets And Highways Code >> Division 17. >> Chapter 7.
31475
. (a) Toll revenues from a project may be used to reimburse or
finance the costs of state agencies and federal agencies incurred in
connection with the implementation or operation of a project,
including reimbursement of federal funds specifically allocated to
SANDAG for a project by the federal government or other funds from
funding sources that are not otherwise available to state agencies
for transportation-related projects. SANDAG shall be reimbursed for
administrative costs in an amount that shall not exceed 3 percent of
project revenues.
(b) Toll revenues shall be used to pay for costs in the categories
below in the following priority:
(1) Payments pursuant to bonds and resolutions, indentures, and
other constituent instruments defining the rights of the holders of
bonds and any repayment or reimbursement obligations of SANDAG to any
providers of bond insurance or letters of credit or lines of credit
related to bonds.
(2) SANDAG costs for operations, toll collection, and
administration of the facility.
(3) Reimbursement to federal, state, and local agencies for costs
incurred by those agencies for services provided to a project that
are reimbursable pursuant to a written agreement between SANDAG and
the respective agency.
(4) Costs for capital improvements to repair or rehabilitate a
project, to expand project capacity, to improve project operations,
or to increase public transit and nonmotorized options in the
corridor.
(5) Excess revenues shall be used pursuant to the plan approved by
the board pursuant to subdivision (b) of Section 31476 that
specifies the expenditure of toll revenues for projects that increase
transportation options in the corridor, including, but not limited
to, public transit and nonmotorized transportation that would result
in reduced vehicle miles traveled.