Section 46382 Of Article 10. Interim Project Assessments From California Water Code >> Division 14. >> Part 9. >> Chapter 2. >> Article 10.
46382
. If there are no obligations outstanding which are secured by
an interim project assessment, the board may, at any time and
without notice or hearing, order that the uncalled balance of such
interim project assessment be canceled and that the amount of the
credit against the original assessment represented by such uncalled
balance of said interim project assessment be annulled for each tract
of land in the district. In such event, notwithstanding the
provisions of Section 46379, the amount of said original assessment
to be collected from each tract of land in the district shall be
increased by the amount of the credit that was so annulled; provided,
however, said amount shall be decreased by the amount of any payment
made on the uncalled balance of said interim project assessment.
Interest due on the recomputed collectible amount of said original
assessment shall be computed as provided in Section 46671 or 47303 as
the case may be.