. (a) A reclamation district specified in subdivision (d) may
construct, maintain, and operate a plant for the generation of
hydroelectric power, together with transmission lines for the
conveyance thereof and with other facilities that may be necessary or
appropriate for the construction, maintenance, and operation of that
plant. Construction of the plant and transmission lines may be
financed by the issuance of time warrants pursuant to Article 3
(commencing with Section 53040) of Chapter 1 of Part 9 to pay the
cost of construction of the plant, transmission lines, and related
facilities, except that the board may, by resolution, provide for the
payment of those time warrants solely from the proceeds derived from
the operation of the hydroelectric powerplant, in lieu of the
assessment described in Section 53040, and may, in that event, pledge
the plant, transmission lines, and related facilities and the
revenues from the operation of the hydroelectric plant as the sole
security for the payment of the time warrants.
(b) The hydroelectric plant, transmission lines, and related
facilities constructed pursuant to this section may be leased for
operation to, or the power generated may be sold to, a public utility
or public agency engaged in the distribution, use, or sale of
electricity, but shall not be offered for sale directly by the
district to customers other than a public utility or public agency.
(c) Proceeds from the sale of electricity shall be utilized to
retire any time warrants issued for construction of the facilities
and otherwise for the powers and purposes for which the district was
formed.
(d) This section applies only to Reclamation District No. 1004
acting in conjunction with the County of Colusa.
(e) This section shall become operative on January 1, 2021.