Section 6352 Of Article 1. New Or Enlarged Dams And Reservoirs From California Water Code >> Division 3. >> Part 1. >> Chapter 7. >> Article 1.
6352
. As soon as possible after giving notice of completion, the
owner shall file an affidavit with the department stating the actual
cost of the dam or reservoir in such detail as the department
requires to determine whether a further fee is due. In the event the
owner of a new or enlarged dam or reservoir, because of loss of
records, recent change of ownership, or other causes beyond his
control, is unable to report the actual cost of construction or
enlargement, he shall file an affidavit to this effect, stating the
reasons therefor, within 30 days after receiving a written request
therefor from the department. The department shall then make its own
appraisal of the cost of construction or enlargement and determine
what further fee, if any, is required. Upon making a determination
that a further fee is required, the department shall notify the owner
by certified mail of the amount of such fee within 15 days and shall
notify the owner that he may appear within 60 days thereafter before
an authorized representative of the department to protest the amount
of the fee, in whole or in part, determined by the department to be
required, and the sufficiency of the appraisal upon which such
determination was based.