Section 81674 Of Chapter 5. Miscellaneous From California Water Code >> Division 31.7. >> Chapter 5.
81674
. (a) San Francisco shall submit a report to the Joint
Legislative Audit Committee on or before September 1 of each year
describing the progress made on projects financed by the authority
and on the implementation of the capital improvement program for the
regional water system.
(b) With regard to the projects financed by the authority, San
Francisco shall include in the report, to the degree feasible, all of
the following information:
(1) The expenditure of the bond proceeds.
(2) The expenditure on each project relative to budget and
schedule.
(3) A description of the physical portion of each project
completed compared to schedule.
(4) Significant revisions to a budget or schedule, including the
reason for the change and the plan or effort taken to complete the
project in accordance with the original budget and schedule.
(5) A description of potential service impacts of schedule delays
and measures planned or being taken to reduce the risks of long-term
service interruptions.
(6) The plan for work remaining, including projected schedule and
cost for each project completion relative to original budget and
schedule.
(c) With regard to the implementation of the regional water system'
s capital improvement program, San Francisco shall include in the
report all of the following information:
(1) The status of current projects, without regard to the source
of financing.
(2) Modifications to the capital improvement program relative to
the capital improvement program adopted by the San Francisco Public
Utilities Commission in May 2002, noting the significance of any
change in schedule and project completion dates that decrease or
increase the risk of long-term service interruptions to the customers
of the regional water system.
(3) A description of measures planned or taken to reduce risk if a
project is delayed.